Most clinics discover their instrument throughput only when it fails. The schedule looks fine on a normal Tuesday, and then the sterilizer throws a fault at 9:40, or the ultrasonic cleaner is out for a service visit, and by 11:00 there are two rooms waiting on instruments and one person explaining to a patient why the appointment is moving. Throughput planning is the work of knowing, before that morning, how many instrument sets an hour the practice can actually produce, which step limits it, and what the practice does when one step disappears.


This article sets out how to measure the constraint properly, how to size the buffer between procedures and reprocessing, and what a one-page breakdown plan should contain. It is about the arithmetic and the decision, not about buying a second sterilizer as a reflex — in many practices the constraint is not the chamber at all.
The measurement starts with the workflow, because instrument throughput is not the sterilizer's cycle time. A set passes through collection and transport, cleaning, inspection, packaging, sterilization, and release, and each of those has a duration and a queue in front of it. CSA Z314:23 treats the reprocessing system as the whole of that chain for Canadian health care settings, and ISO 17665:2024 requires the sterilization process to be developed, validated and controlled — which includes knowing what the process is expected to deliver per day, not only that it reaches temperature.
Where does the constraint actually sit?
The constraint is the step whose capacity, in sets per hour, is lowest, not the step that looks most technical. In dental practices it is frequently cleaning and packaging rather than the chamber: one ultrasonic bath with a fixed basket, one sealer, one person doing inspection and pouching while also answering the phone. A 6 L benchtop ultrasonic bath and a constant-heat 12 mm pouch sealer are the two capacities that quietly decide the day.
| Step | What sets its capacity | What to measure | Typical hidden loss |
|---|---|---|---|
| Collection and transport | Who carries, how often, whether contaminated items wait at the chair | Minutes from end of procedure to arrival at the reprocessing area | Items waiting in a treatment room, out of sight of the workflow |
| Cleaning | Bath volume, basket size, cycle length, number of baths running | Sets or instrument units cleaned per hour | Bath changes, over-full baskets, chemistry that foams and damps cavitation |
| Inspection and packaging | One trained person, one sealer, pouch size changes | Pouches sealed per hour, including labelling | Rewrapping after a failed seal, hunting for the right pouch size |
| Sterilization | Chamber volume, cycle length, load pattern | Loads per hour at the practice's real cycle | Partial loads run to keep up, which wastes chamber capacity |
| Drying and cooling | Cycle design and how the load is handled after | Minutes from cycle end to handling | Pouches handled warm, which compromises the seal and the barrier |
| Release | Monitoring method and the practice's release rule | Time from cycle end to instruments usable on a patient | Releasing on chemical indicators while waiting for a biological result, without a written rule |
How do I size the buffer between procedures and reprocessing?
The buffer is instrument inventory, and it is what turns a breakage or a service visit from a cancelled day into a delayed one. The arithmetic is simple enough to do on one page: how many procedures run concurrently at peak, how many sets each needs, how many sets are in reprocessing at any moment, and how many are on the shelf. The number of sets a practice owns should cover peak demand plus the sets in transit through the workflow — and then some, because the workflow is where the variance lives.
A worked illustration, with numbers that are chosen to be easy rather than to describe any particular practice: three rooms, each changing over every 45 minutes, with one instrument set per procedure, is four sets an hour. If the workflow takes 90 minutes from chair to shelf, then six sets are always in the workflow. Peak demand of four an hour during a busy morning, against a workflow that produces four an hour only when nothing goes wrong, means the practice is running at the exact limit — and a limit is not a margin.
Two rules of thumb follow, and both are about behaviour rather than equipment. First, capacity measured at the average is capacity that fails on the busy day; size to the peak morning, not to the weekly average. Second, treat a partial load as a cost: running the chamber half full to save ten minutes raises the cost per set and does not create capacity at the constraint, which is usually downstream of the chamber.
What should the breakdown plan say?
A one-page plan is enough if it answers four questions: what happens to the load in the chamber, what happens to the day's cases, who decides, and what the practice uses while the equipment is down. The fourth question is where most plans are thin. Alternatives have different costs and different constraints: a second chamber in the practice, a neighbouring practice or a hospital department that will process under an agreement, contract sterilization with the transport time it implies, or single-use alternatives for a defined block of work.
| Situation | Immediate action | What must be decided, and by whom |
|---|---|---|
| Chamber faults mid-cycle | Do not open the door; record the fault code and the cycle parameters; treat the load as not sterile | The reprocessing lead decides on re-cleaning or re-packing after the fault is diagnosed |
| Chamber out for the day | Switch to the documented alternative; move non-urgent cases; notify the clinical lead before the first affected patient | The clinical lead decides which cases are deferred, and records why |
| Ultrasonic bath out | Reduce the day's instrument volume; use the validated manual cleaning method if one exists in the procedure | The reprocessing lead confirms the manual method is the validated one for those devices |
| Sealer out | Do not substitute tape or a household sealer; use pouches that require no heat seal only if the device instructions and the pouch IFU allow it | Practice lead decides whether to defer procedures that need pouched instruments |
| Monitoring supplies short | Follow the deviation procedure; do not release loads without the monitoring the procedure requires | Accountable person records the deviation and the rationale |
What does the plan depend on that clinics forget?
Two dependencies are usually overlooked. The first is the release rule: if a practice releases loads only after a biological indicator is read, then the turnaround time includes the incubation period, and no amount of chamber speed changes that. The rule has to be written down, including what happens during a period when the indicator result is pending, because that is the decision a locum will face at 5 pm on a Friday.
The second is people. A plan that assumes one trained person is available every day is a plan with a single point of failure that happens to draw a salary. Cross-coverage, a documented competency check for the second person, and a record that shows who was assessed is the only version of the plan that survives a holiday week. CliniEco Medical supplies the bench equipment and consumables described above and distributes them under Health Canada MDEL #35334; the capacity figures come from measuring the practice's own workflow, and the release rules come from the provincial requirements and the practice's written procedure.
Where does a practice take this next?
Three things a clinic can act on rather than read: a printable compliance log sheet that records bath changes, biological indicator results and the operator for each cycle, and exports from the browser; the clinic supply planner that turns daily bench counts into cases per month; and, where a finding has to be documented for an inspector, Ask your compliance question which returns a written answer citing the regulation or standard it rests on.
Facility and multi-site buyers can Wholesale and multi-site ordering for case pricing and account setup. Reselling? become a distributor.
Related reading
- Can one pouch sealer keep up with two autoclaves in a dental clinic?
- When must a Canadian clinic take a sterilizer out of service?
- How should a clinic handle a backorder on a critical sterilization consumable?
- What should a sterilization log look like in a three-chair clinic?
Frequently Asked Questions
Should we buy a second sterilizer to fix throughput?
Only if the chamber is the constraint. In many practices the limiting step is cleaning and packaging, so a second chamber adds cost without adding sets per hour. Measure each step in sets per hour across the real workflow, then spend at the constraint — a second bath, a second sealer or another trained person may produce more instrument capacity than another chamber, for less money and less floor space.
How many instrument sets should a practice own?
Enough to cover peak concurrent procedures plus everything in the reprocessing workflow at that moment, with a margin for variance. The mistake is sizing to the average day: capacity that matches the average fails on the busy day, and the busy day is the one where a cancelled appointment costs most. The calculation takes one page and is worth redoing when the number of rooms or the procedure mix changes.
Does the biological indicator delay affect how many instruments we need?
It affects the release rule, and therefore the turnaround time. If loads are released only after the biological indicator is read, the incubation period sits between the cycle and usable instruments, so the practice needs enough sets to cover it. Whatever the practice's rule is, it should be written down together with the alternative during the pending period, so the decision is not made ad hoc at the end of the day.
What is the least expensive form of redundancy?
Usually the one that does not require capital: a written agreement with a nearby practice or hospital department, a qualified contract sterilization provider with a known transport time, and enough monitoring and packaging stock to process a catch-up load when the equipment returns. A second machine is the most complete answer and the most expensive; a documented alternative that has been tested once is worth more than an untested agreement.
How do we know the alternative route is acceptable?
It has to produce the same validated outcome for the devices concerned: the same level of cleaning, the same validated sterilization process for the device, and the same monitoring and release evidence. A route that is faster but unmonitored is not redundancy, it is a different process. Record the alternative in the written procedure, name who may authorise it, and keep the monitoring records from the period it was used.
Sources
- CSA Group, CSA Z314:23, Canadian medical device reprocessing (reprocessing system, records and professional office scope) - International Organization for Standardization, ISO 17665:2024, Sterilization of health care products — Moist heat (development, validation and routine control of the sterilization process) - International Organization for Standardization, ISO 11607-2:2019, Packaging for terminally sterilized medical devices — Part 2: validation requirements for forming, sealing and assembly processes - Public Health Ontario, provincial guidance on cleaning, disinfection and sterilization of medical equipment and devices in all health care settings - Royal College of Dental Surgeons of Ontario, infection prevention and control standard - Centers for Disease Control and Prevention, Guideline for Disinfection and Sterilization in Healthcare FacilitiesCliniEco Medical distributes clinic, laboratory and care-home consumables in Canada under Health Canada MDEL #35334. Requirements that bind a particular practice remain the ones in its own written procedures and in the rules of the province where it operates.